Wednesday, 18 December 2013

High Court decision deferred till New Year

The High Court case concluded at 1pm today, with the Judge Wyn Williams adjourning his decision until some time in January.  Yesterday, we had good coverage on BBC Wales and today an article in the Echo:
Barrister Alex Goodman whose acting on behalf of CATI’ Pauline Ellaway told the Judge that Cardiff council had flouted regulations and allowed waste management firm Viridor to build in Splott when it should not have done so.
Dubbing the council’s actions “procedurally inept” he claimed the authority’s reports and consultation process were flawed and that it failed to stop work when it should have.
Mr Goodman said CATI’s “submissions fell on deaf ears because work was allowed to proceed.  No robust action was being taken in respect of development that was continuing apace.” 
Best thanks to our Pauline for staying the course!

Tuesday, 17 December 2013

High Court hearing –first day – points advantage for CATI.



FIRST DAY NEWS FROM HIGH COURT      Tuesday 17 Dec.
Pauline’s lawyer, Alex Goodman, laid out his case for much of today, explaining why Cardiff Council’s repeated delay to enforce against Viridor’s unlawful building work and failing to require retrospective permission was unique in British law.  Then Cardiff Council’s lawyer took 80 minutes, making brash assertions, some obviously in error, and was unable to grapple with the detailed legal points of our side.  The Cardiff Council ethos - assert authority with confidence - to steamroller criticisms.  Tomorrow comes Viridor’s lawyer, rumoured to be costing over £200 000.  
     The Court starts at 10am and is expected to complete the case in the morning – if you can, do call in and support Pauline’s team!

Cardiff council attacked over city incinerator


Authority should 'quash' decisions that allowed to work to start as they were taken unlawfully, hears High Court

The Trident Park Energy from Waste Facility development
The Trident Park Energy from Waste Facility development
Cardiff council must “quash” decisions that allowed work to construct an incinerator to begin because they were taken unlawfully, Cardiff High Court heard today.
In an action brought by Cardiff Against The Incinerator campaigner Pauline Ellaway, barrister Alex Goodman told Judge Wyn Williams the authority had flouted regulations and allowed waste management firm Viridor to build in Splott when it should not have done so.
Dubbing the council’s actions “procedurally inept” he claimed the authority’s reports and consultation process were flawed and that it failed to stop work when it should have.
Mr Goodman insisted CATI’s “submissions fell on deaf ears because work was allowed to proceed.”
“No robust action was being taken in respect of development that was continuning apace,” Mr Goodman said.
Construction of the £185m plant started in July 2012 before planning conditions had been met.
Developers must “obtain consent and then commence works,” Mr Goodman insisted. “It is a simple sequence,” he said.
CATI’s solicitors repeatedly sent letters requesting enforcement be taken.
“Throughout the claimant has taken considerable action to encourage the council to take action,” Mr Goodman said.
“The council has always acknowledged it was unlawful and that the development was at risk.”
Despite this Mr Goodman said the authority allowed work to go ahead.
He claimed Viridor was allowed to report whether anything of archaeological import was discovered during building work – rather than this being the responsibility of an independent body.
And this was done after building work started.
“It is appropriate for the court to quash these decisions, Mr Goodman said.
But Simon Bird QC, for Cardiff Council, insisted the authority had done nothing wrong.
“All substantive information was supplied to the council prior to commencement,” he said.
He dismissed arguments public notices had not been formulated properly.
“There is no suggestion CATI were labouring under any misapprehension over what adverts meant or had any difficulty in responding,” he said.
Outside court Pauline Ellaway said: “The council cannot get away with flouting the law for a mega-company.”
The hearing continues tomorrow.

Thursday, 12 December 2013

For all CATI supporters on Facebook: 
do please spread invites to this event to your friends
Pauline v Cardiff Council in the High Court
https://www.facebook.com/events/552464244842006/

And everyone - please inform your friends of our Days-in-Court, spearheaded by Splott's Pauline "Mrs Incinerator" with leading law firm Richard Buxton's.  Invite them to come and join us at the start on Tuesday 17th (9.30 for photo-shoot/TV) or drop in later  for an hour or so during Tuesday and Wednesday!
And wish us luck!  

letter to Echo
Goodway adds spice to our Case
Russell Goodway signed a £500million contract with Viridor just a week before the challenge in the High Court, with full judicial hearing opening on Tuesday 17th?  I guess Goodway rushed it because it’s likely the Court will judge Cardiff’s planning permission to be unlawful.
Acting quickly to avoid Court Orders is all too common in businesses operating on the margin.  But can Goodway escape so easily when subject to ‘malfeasance in public office’ and ‘due diligence’ tests?
This costly contract gives extra spice to the Court hearing -   give Pauline support and hear her legal team tearing into the Council and Viridor for building without permits!
The law must make big Councils treat mega-companies just like they do small firms who build without approved plans!

Tuesday, 10 December 2013

Prosiect Gwyrdd Unlawful - costly day for taxpayers

On the day Prosiect Gwyrdd led by Russell Goodway gets the Go ahead for Prosiect Gwyrdd..


South Wales WIN says:
This will prove a very costly day for taxpayers in Cardiff and the other Councils. Max Wallis added 
"The bureaucrats have forced through a 25-year promise to send wastes for old technology
 incineration, a dismal 22% efficient in energy terms. Cllr Russell Goodway, 
Chairman of the Joint Committee is wrong to say they will make significant savings from this project."

Anne Greagsby said "Much of the promised wastes are recyclable materials and we expect that 
increasingly stricter requirements on recycling will ban burning of them. Like other Councils 
in England who contracted for excessive tonnages of waste, future councils in Cardiff, 
Newport, Caerphilly, Monmouth and the Vale of Glamorgan will have to try and escape
from this huge long-term burden." 

Response from SNIC  :
 "Rob Hepworth, the Bishton-based Chair of Stop Newport and Monmouthshire Incinerator 
Campaign (SNIC) warned that this was not the end of the story. He said 
" What more can you expect from a cabal of profiteering corporate interests and biased officials 
 who want to impose waste policies on SE Wales that are at least 20 years out of date?
SNIC believe the decision is illegal as well as perverse. If it is allowed,  we will pay an
unacceptable price in terms of  cancer deaths, increased carbon emissions,
lower recycling and higher taxes on Newport & Monmouthshire people.”

SNIC Vice Chair Haydn Cullen-Jones of Monmouth added 
“We will  be sending today’s announcement to the European Commission as we believe it 
constitutes,  unagreed and hence unlawful, state aid to a private, speculative waste
incinerator already under construction in Cardiff.  Sadly PG have settled for the next
worst solution to landfilling residual waste and guaranteed £400m of taxpayers
money into the bargain." Monmouthshire is already close to the 2025 70% target for
recycling and hence will end up paying more and more per tonne of residual waste
for the next 25 years. While incineration in the guise of Energy from Waste
is so heavily subsidised, it is no surprise that other more financially and
environmentally viable processes have been disregarded."

Contact SNIC - Rob Hepworth  01633 413253 rghepworth@gmail.com

Future future plans for a district heating network are total fantasy as the cost 
would be enormous 

5% Recycling from bottom ash with no market for use as aggregate for 
building materials 

Silence on toxic ash - where will it go? 

Produces significant quantities of CO2.

Long-term council contracts to provide waste for incinerators will 

discourage waste reduction, reuse and recycling efforts.

Viridor signs 25-year Prosiect Gwyrdd EfW deal

THE BIG ISSUES THAT GOODWAY hasn't answered
Prosiect Gwyrdd contract with Viridor

Dear Cllr Goodway,
We believe that you as chair of PG take ultimate responsibility for the key financial issues being properly
 checked prior to signing the huge contract with Viridor.
The answers on two basic financial issues appear to be outstanding  
1. State Aid – the risk of the European Commission ruling the 25% WG subsidy to be illegal has
not been accessed by Accounting officers
2. No updated Value-for-Money assessment has been made, neither by the Project or by the WG review.
You should be aware that the National Audit Office has just announced it is investigating 
three 25-yr incinerator contracts in England 
www.nao.org.uk/press-releases/defras-oversight-pfi-waste-projects/;
also that Defra withdrew WIC (waste infrastructure credits) last week for the Norfolk CC’s incinerator, 
putting Norfolk CC in trouble over their recent 25-yr contract  
www.letsrecycle.com/news/latest-news/councils/defra-withdraws-ps169m-norfolk-efw-funding
You may have seen that EdF yesterday specified the State Aid issue as needing a decision 
before they sign the Hinkley Point nuclear deal.
We question that the Project officers are capable of giving appropriate advice on these 
issues and suggest appropriate independent experts should be consulted, eg. the WAO 
who are already considering the PG contract.
From Cardiff Against the Incinerator CATI

Monday, 9 December 2013

Pauline v Cardiff council Tues 17 Sept High Court

 MEDIA BRIEFING by Cardiff Against the Incinerator - CATI

Pauline v Cardiff council

Splott incinerator protesters take Cardiff Council to the High Court

Rob Griffiths, from CATI said: “CATI is taking Cardiff council to court in order to protect local residents, businesses and the environment.”

 The full legal hearing to quash Cardiff's approval of the Viridor waste incinerator [1] is now scheduled to start Tuesday 17 December, for two days in the Cardiff High Court.

 Dave Prosser, Pauline, Anne, Max 


The leading environmental and public law firm, Richard Buxton, is representing CATI member, Pauline Ellaway.  
The full hearing should consider whether “the process adopted by the Defendant Council amounted to an impermissible extension or addition to any previously-recognised exception to the Whitley principle”. 

(Viridor) in the first place in proceeding to begin works prematurely, as they did, and of the Defendant Council (Cardiff) in protesting only after being prompted to do so by CATI, and then effectively condoning such conduct in the ways in which it subsequently dealt with matters”, raises questions of the Council’s “procedural propriety”

CATI opposed the incinerator in principle, Dave Prosser a CATI campaigner said  “We feel betrayed by Cardiff Council’s completely inadequate consultation of the public over this matter of high public concern and in pushing through approval of the incinerator in the Splott/Cardiff Bay area despite the large population potentially harmed by the pollution” [4].  The Ombudsman decided in 2012 on a complaint from CATI that the Council was guilty of maladministration, causing an injustice to residents [5].  The Council had to apologise to individuals but failed to reconsider and change their poor practice.

This High Court hearing is, however, confined to technical issues of planning law.  Anne Greagsby CATI campaigner points out  “CATI accuses Cardiff Council of undermining the law by allowing building work to proceed without the necessary permits and permissions.”

Max Wallis a CATI campaigner said   “The whole planning permission process has been an undemocratic shambles. The wishes of local people and businesses have been ignored and councillors have tied themselves in knots as officials steamrollered Viridor's scheme through the Council.”

<iframe width="560" height="315" src="//www.youtube.com/embed/ckCQVkYuljQ?rel=0" frameborder="0" allowfullscreen></iframe>

Contact
CATI - Cardiff Against the Incinerator e-mail: cardiffagainsttheincinerator@gmail.com
Rob Griffiths  07790 884137 
58 Janet Street Splott Cardiff
Pauline Ellaway  07837 346114  20 Bayside Road,  Bayside Estate, Cardiff CF24 5NA
Max Wallis 07714 163254 or 02921 156265 or 02920 190087
Dave Prosser   07504 323422 
                                         
twitter:@nocardiffburner
Blog 
http://cardiffagainsttheincinerator.blogspot.com/


 NOTES
[1]  Waste incinerator under construction at Trident Park, between Splott and Cardiff Bay, at a cost of £185 million.  Construction started in July 2012, just as further ‘subsequent’ planning applications were published for consultation.  These were not approved till Feb. 2013; the Court case challenges them as legally flawed.
[2]  Judge Curran approved for a full expedited hearing of the request to the Cardiff High Court lodged on 26th  March for the following:
a)      An order quashing the grant of subsequent applications approval dated 25 February 2013;
b)      A declaration that the decision of the Council to treat the subsequent applications approval as retroactively permitting the unlawful works and rendering enforcement action inexpedient was unlawful;
c)      An order requiring the Council to reconsider enforcement action against the unlawful works;
d)      An order directing the Council to issue an enforcement notice and/or stop notice prohibiting further continuation of unlawful development
[3] Full judgment 27 Sept’13  [2013] EWHC 2907(Admin)  at  <high-court-justice.vlex.co.uk/vid/-465183198>
[4] Entirely unsuitable for the Splott and Cardiff Bay site on grounds of lorry traffic, flood risk, hazard to health and processing  hazardous ash.

Wednesday, 4 December 2013

Labour wont support Pauline in Splott against the Incinerator

Two Candidates support CATI against the Incinerator
Splott By-election.  
Only UKIP and TUSC candidates - Brian Morris and Katrine Williams  - are concerned to oppose the Viridor waste Incinerator, bringing wastes from over S-E Wales to burn in our city.  
 The Lib-Dems started the project and Labour continued it with Tory support; all want to give Viridor a long-term contract to burn the city's waste, despite the toxic fumes, waste lorries trucking through the city and huge tonnages of incinerator ash with toxic dust.  Apart from Neil McEvoy for Plaid, Cardiff politicians rubber-stamped a Viridor contract of several £100 millions for 25-years.  Extraordinary irresponsibility with Council funds, and in contracting for tonnages far higher than expected to be produced in future years. Result of brown envelopes or blind party-voting?  

CATI hasnt heard anything from  the labour candidate who works for a Islwyn Labour AM Gwyn Price. As soon as Labour got into office they voted to privatise residual waste Prosiect Gwyrdd - without any scrutiny, locking Cardiff into payments for burning waste for the next 25 years in a PFI style contract. Labours Gretta Marshall, Luke Holland and Huw Thomas all failed to vote against it. Surprise! Russell Goodway is chair of the 5 council Prosiect Gwyrdd group. 

No support either from FibDem Jamie Matthews  or Tory Daniel Mason 
Nearby Bayside Estate resident Pauline Ellaway, supported by CATI, is taking Cardiff Council to the Cardiff High Court on 17-18 December.



PartyCandidate
IndependentElys John
ConservativeDaniel Mason
Lib DemsJamie Matthews
UKIPBrian Morris
LabourEdward Stubbs
TUSCKatrine Williams

Sunday, 1 December 2013

Pauline v Cardiff Council in the High Court

Full legal hearing to quash Cardiff's approval of the Viridor incinerator as unlawful - and stop the construction - opens on Tuesday 17 December in the Cardiff High Court.
Leading environmental lawyers, Richard Buxton, are representing CATI member, Pauline Ellaway.  In the first stage High Court verdict on 1st October, Judge Curran was appalled at the Council's catalogue of errors.  Do come along and encourage the full hearing for orders on the Council.  Do drop in on the Court hearings for an hours or two, during 10am-4pm on the two days 17-18 December.

Keep a lookout for updates here or via Twitter
Contact 
Cardiffagainsttheincinerator@gmail.com
Pauline Ellaway 07837 346114
Max Wallis 07714 163254
Dave 07504 323422 or via william.prosser@btinternet.com
Anne Greagsby 029 20190087


Friday, 25 October 2013

Russell Goodway highly Secretive over Financial Risks of illegal State Aid

FINANCE AND ECONOMIC DEVELOPMENT WRITTEN QUESTIONS: COUNCIL, 24 OCTOBER 2013
W18 WRITTEN QUESTION FROM COUNTY COUNCILLOR McEVOY

Could you outline legal written advice given regarding Cardiff’s financial exposure with Prosiect Gwyrdd and allegations of the Welsh Government grant contravening state aid rules?

Reply
I am advised that any such advice would be covered by legal professional privilege and it would not be appropriate for this to be disclosed publicly.

Note - 'priviledge' is not absolute: "Legal Professional Privilege (“Privilege”) entitles a client to refuse to disclose certain confidential, legal communications...  It protects confidential communications between a lawyer and his client provided that the communications are for the purpose of seeking and receiving legal advice in a relevant legal context." 
Why the false answer from Goodway, if not to mislead?

Tuesday, 8 October 2013

Council chief blunders in citing Sheffield’s city incinerator

Cllr Michael is on risky ground in referring to Sheffield’s city incinerator (in Echo of 3rd Oct.) 
Bad emission levels – the worst in England - were tolerated by that Council until Greenpeace staged an occupation in 2001, raising public consciousness and forcing its closure.  The replacement incinerator operated by Veolia does have problems and cannot obtain enough waste from the permitted waste area.
This has lessons for Viridor’s incinerator in Cardiff.

Veolia assured Sheffield Council in 2002 they would make up any shortfall in domestic waste from local C&I (commercial and industrial) waste, to justify a new 225 000 tpa incinerator compared with the old 125 000 tpa (tonnes per annum).   How wrong they were!  In 2010 Veolia required permission from the Council to import waste from outside the Sheffield waste area.  In 2012 Veolia sought permission to import waste from even further, into Nottinghamshire, as waste reduction measures in Sheffield were successful and recycling rates in commerce and industry rose.

Likewise, Viridor assured Cardiff in 2010 that they would make up any shortfall in domestic waste from C&I waste from S-E Wales.   They failed to provide any assessment, but comparison with the Sheffield-Rotherham-Chesterfield-Nottingham area suggests that Viridor too will fail.

Cardiff was so keen to get an incinerator that they allowed a 350 000 tonne pa monster, over 50% larger than Sheffield’s.  Viridor are unlikely to find sufficient waste to fuel it, so will return to Cllr Michael’s planning committee for permission to import waste from afar, just as in Sheffield.

What a blunder, Cllr Michael, to refer to Sheffield city’s incinerator!

Tuesday, 1 October 2013

High Court judge rules for CATI: slates Cardiff Council/Viridor

We win our long delayed application for an emergency hearing!
Judge Curran agreed that Pauline Ellaway is a 'standard bearer' for many other members of the
 public who are deeply concerned about the incinerator development.
He ordered an emergency full hearing of Ms Ellaway's case at which all issues will be 
considered.
The Judge said “the actions of Viridor in the first place in proceeding to begin works prematurely
as they did, and of the council in protesting only after being prompted by CATI, and then 
effectively condoning such conduct” raise issues of “procedural propriety”
(see Walesonline/Echo report).
CATI is pleased that the Judge ruled the Hearing should cover most of our points,
though not our maximum demand for an immediate stop on the building work
(full judgement below).
Dave Prosser of CATI said: “the judge slapped down the Council's assertion that our objections
were 'unarguable'. Their planning committee had the legal case before them at their meeting
in February, but led by their chair Cllr Michael Michael, failed to seek proper advice before
they dismissed it, deciding then to risk public money on a court case”.
Max Wallis of CATI added:
The judge has knocked another hole in Cardiff Council's plan to sign a contract with Viridor;  
the High Court judge finds the company acted unlawfully in starting building works last July, 
action that Cardiff Council condoned by refusing to stop it. It's a further reason for 
the five Councils in Prosiect Gwyrdd to question the £600million 25-year contract to incinerate
excessive tonnages of waste.”
CATI Statement and full judgment below or online 
-------------------------------------------------------------------------------------------------------------
High Court judge rules for CATI

We win our long delayed application for an emergency hearing!

Judge Curran agreed that Ms Pauline Ellaway is a 'standard bearer' for many other members 
of the public who are deeply concerned about the incinerator development.
He ordered an emergency full hearing of Ms Ellaway's case at which all issues will be 
considered. The legal firm Richard Buxton Environmental and Public Law who are
acting for Ms Ellaway are proposing a December dates for the hearing in Cardiff High Court.
The Judge said “the actions of Viridor in the first place in proceeding to begin works 
prematurely, as they did, and of the council in protesting only after being prompted by 
CATI, and then effectively condoning such conduct” raise issues of “procedural propriety”.
CATI is pleased that the Judge ruled in favour of most of our points, accepting the Hearing
would cover
  1. An order quashing the grant of the subsequent applications approval;
  2. A declaration that the decisions of the Council on 13 February to treat the proposed 
    subsequent applications approval as retroactively permitting the unlawful works 
    and rendering enforcement action inexpedient was unlawful;
  3. An order requiring the Council to reconsider enforcement action against the unlawful 
    works.
Dave Prosser of CATI said: “the judge slapped down the Council's assertion that our objections
were 'unarguable'. Their planning committee had the legal case before them at their meeting
in February, but led by their chair Cllr Michael Michael, failed to seek proper advice 
before they dismissed it, deciding then to risk public money on a court case”.
Max Wallis of CATI added:
“The judge has knocked another hole in Cardiff Council's plan to sign a contract with Viridor, 
with the High Court judge finding the company acted unlawfully in starting building works 
last July, action that Cardiff Council condoned by refusing to stop it. It's a further reason
for the five Councils in Prosiect Gwyrdd to question the £600million 25-year contract to 
incinerate excessive tonnages of waste.”
Cardiff's Cllr Govier stated* that 80% of Cardiff's black-bag wastes is recyclable, yet the 
recycling plans would take out only 30% of it (increase the current 50% recycling to 65% only)
and send the remainder of which half is 'recyclable' to the incinerator. It follows the 
proposed contract figures should be halved. As the other Councils' proposed guaranteed 
waste tonnages are similarly over-high, they should all be demanding a review of the 
proposed contract.**

At the emergency hearing of the case in Cardiff High Court, Dave Prosser of CATI will testify
 to the extent of the unlawful building works, which Cardiff did nothing to check and stop.
Max Wallis will testify how CATI has found the Council ignoring and misrepresenting criticisms, 
disregarding their duties to protect the environment and health from Viridor's incinerator.
The Community is required to raise £3000 to towards the costs of the legally-aided case
spearheaded by Pauline Ellaway; CATI is appealing for further donations [4].

CONTACTS
Max Wallis 07714163254
Rob Griffiths 07790 884137
David Prosser (Press officer) on 029 20791993 (h), 07504 323422 (m)
Pauline Ellaway (Claimant) on 07837 346114
Lisa Foster (Buxton lawyers) 07970 097402

/ FURTHER INFORMATION
** The Councils' claims of “savings” from the £600million year incineration contract are 
completely fictitious, as the greatest savings come from avoiding incineration costs through 
sorting the waste and selling it for recycling, as Cllr Govier now proposes.

The High Court decision, if it goes in favour of CATI, will be ground-breaking in ensuring 
Councils follow the law rather than political motivations. It will set back the Viridor project 
to square 1, when the Councillors can turn it down as entirely unsuitable for the Splott and
Cardiff Bay site [3].

It will also extricate Cardiff from the 25-year contract to incinerate large tonnages of waste rather
 than reduce and recycle waste in accord with policy. No-one can justify long contracts when 
waste processing is changing rapidly towards recycling. While other councils try to re-negotiate
 such contracts, Cardiff’s current leaders rush to sign one. They may well be caught because
the subsidy offered by the Welsh government is unapproved by Europe so could be
“illegal State Aid” under the European Treaty.
--------------------------------------------------------------------------------------------------------------------------------
Support our Community Legal Action <cardiffagainsttheincinerator@gmail.com>


[1] The request to Cardiff High Court, lodged on Tuesday 26th March, was for the following:

* An order quashing the grant of subsequent applications approval dated 25 February 2013;
* A declaration that the decision of the Council to treat the subsequent applications approval as retroactively permitting the unlawful works and rendering enforcement action inexpedient was unlawful;
* An order requiring the Council to reconsider enforcement action against the unlawful works
* An order directing the Council to issue an enforcement notice and/or stop notice prohibiting further continuation of unlawful development.

[2] 25-year contract for £600million between the 5 Local Authorities, of which Cardiff will pay
 about £250 million.

[3] Entirely unsuitable for the Splott and Cardiff Bay site on grounds of lorry traffic, flood risk,
 hazard to health and processing hazardous ash. It's also unsuitable for use of the huge
 quantities of waste heat, because the claims for a city-wide pipe network are unviable
 fantasy, not part of a full district heating scheme meeting the big seasonal variations in demand.

[4] Appeal for our Community Legal Action fund
Please contribute to our £3,000 legal action fund. You can do this by:
  1. Making a donation by cash or cheque (made payable to 'CATI') and sending it to CATI,
    58 Janet St., Splott, Cardiff CF24 2BE.
  2. Donation to an accredited CATI representative (who will have proper ID).
  3. Phoning David Prosser on 029 20791993 (h), 07504 323422 (m) or emailing us at cardiffagainsttheincinerator@gmail.com to arrange a visit.
  4. Paying online into our account (The Cooperative Bank, Sort Code 08-92-99 
    Account No. 65423583) or at the Bank in High Street, central Cardiff.
  5. Paying online via PayPal at www.ukwin.org.uk (add “for CATI/Cardiff” in the
    comment box on second page, called 'Review Donation').

    COURT RULING

    Neutral Citation Number: [2013] EWHC 2907(Admin)
    Case No: CO/1070/2013
    IN THE HIGH COURT OF JUSTICE
    QUEEN'S BENCH DIVISION
    ADMINISTRATIVE COURT
     27/09/2013
    Civil Justice Centre,
    2, Park Street, Cardiff.
    Before :

    HIS HON. JUDGE CURRAN QC
    sitting as a judge of the High Court
    - - - - - - - - - - - - - - - - - - - - -
    Between :


    The Queen on the application of
    Pauline Ellaway
    Claimant

    - and -


    Cardiff County Council

    -and-
    Viridor Waste Management Limited
    (Interested Party)

    Defendant
    - - - - - - - - - - - - - - - - - - - - -

    Alex Goodman (instructed by Richard Buxton) for the Claimant
    Simon Bird QC (instructed by the Chief Legal Officer) for the Defendant
    David Holgate QC (instructed by Bevan Brittan) for the Interested Party


    Hearing date: 12 July 2013
    - - - - - - - - - - - - - - - - - - - - -
    JUDGMENT
    - - - - - - - - - - - - - - - - - - - - -

    Judge Curran
    1. This is a renewed application for permission to apply for judicial review in order to challenge
      planning decisions of the Defendant, Cardiff County Council, in respect of the development 
      of a waste incinerator by the interested party, Viridor Waste Management Ltd (“Viridor”), 
       at a site in Cardiff Bay, including the decision of the defendant council dated 25th February 2013 to revoke pre-commencement conditions, and to approve retrospectively works which have already been performed at the site.

    1. The single judge, His Hon. Judge Jarman QC, sitting as a judge of the High Court, refused
       permission on the papers on 1st May 2013.

    1. In the briefest terms, the history of the matter is as follows. In 2008 an unsuccessful application
       was made for permission to develop an energy waste facility for Cardiff at the same site. 
      Whilst concern had been raised about the potential effect of such a development on the 
      estuary of the River Severn in terms of what is called eutrophication, (which I understand
       to be the process by which airborne particles generated by that proposed development
       may be absorbed in water) and the acidification of the water in the estuary, the actual 
      grounds for refusal concerned in part recycling targets set by the Welsh Assembly 
      Government, and included considerations such as the import of waste from outside
       Cardiff, and the export of what is known as hazardous fly ash. Permission was
       refused in 2009.

    1. On 29 June 2010 the Council granted a full planning permission to Viridor on a new
       application for a major development on the site at Trident Park, Glass Avenue, Cardiff, 
      to include an “energy from waste” (“EFW”) facility; a combined heat and power plant;
       a pre-treatment and recycling facility; an “Incinerator Bottom Ash Recycling plant”; 
      and associated offices. This proposed development differed in a number of respects
       from the previous application.

    1. There were a number of conditions attached to the permission, (“the pre-commencement 
      conditions”) and Viridor were required to obtain approvals from the Defendant Council
       to certain matters before development commenced under the permission. Applications 
      for such approvals under the pre-commencement conditions constituted “subsequent 
      applications” under Reg. 2(1) of the Town and Country Planning (Environmental 
      Impact Assessment) (England and Wales) Regulations 1999 (“the EIA Regulations.”) 
      There was no challenge by judicial review to the actual grant of permission, 
       whether in relation to the EIA Regulations, or in respect of what has been called the 
      ‘Habitats Directive.’

    1. On 19 July 2012 the Council published a consultation notice on the subsequent applications.
       However, in what was on any view a premature move, on 20th July 2012 Viridor began
       operations with works on site. It continued to do so for a period of eight months 
      despite admonitions from the Defendant Council and protests from the Claimant a
      nd her associates.

    1. The Claimant is and has been for some time an objector to the development. She is a member
       of a campaign group, called “Cardiff Against the Incinerator” (“CATI”). She lives close to
       the site in question, and has drawn attention not merely to the environmental impact of the
       development, but also to the fact that the development will be on 4.5 hectares of a 
      20-hectare site, and parts will be within 500 metres of homes and workplaces. She has been 
      granted legal aid to bring these proceedings.

    1. This application for permission to apply for judicial review has been made upon the basis
       that Viridor had not obtained the necessary approvals from the defendant council for the
       subsequent applications works, and that the defendant council should have issued (and still
       should issue) enforcement proceedings or a stop notice in respect of those works. Complaint
       is made that the Defendant acted irregularly and unlawfully in terms of procedure in 
      retrospectively approving these works.

    1. The applications for approval under the pre-commencement conditions were not, it is common
       ground, subjected to the procedure required by the EIA Regulations before July 2012. 
      But by then Viridor had supplied, so Viridor says, the substantive information needed to 
       support the applications. It had not, however, supplied a “Non-Technical Summary” of
       that information, as was required by the procedure. Under the relevant procedural scheme
       the defendant council should have advertised and consulted on the information submitted

    1. CATI sent what was described as a “Notice Prior to Action” to the defendant council on 
      12 July 2012 complaining that details submitted under pre-conditions (at that stage solely
      conditions 3, 7, 10 and 11) had not been subjected to EIA procedures. This seems to
      have caused some dismay within the ranks of the defendant Council, and on 17 July 2012 
      the Council notified Viridor that it had been advised that none of the pre-commencement
      conditions had been validly discharged because of the failure at that stage to comply with
       EIA procedure. By then, however, contracts had been entered into by Viridor for the
      development of the site. Although there is no express reference to it, the contemporaneous
      correspondence and other documents from the parties during this period seemed to me to 
      reflect a degree of pressure under which those acting for the Defendant were placed by
      the sequence of events.

    1. Whether I am right or wrong about that, it is clear that, faced with the situation as they were, 
      the defendant council decided that the Planning Committee would make fresh decisions on
       whether to grant approvals under the pre-commencement conditions, after satisfying EIA 
      procedures. Viridor had already submitted a satisfactory Environmental Statement in 
      connection with the application for planning permission in 2010, and substantial technical 
      information during 2011-2012 in support of the applications to discharge the 
       pre-commencement conditions. The only additional information which Viridor needed to 
      submit was the Non-Technical Summary.

    1. The Claimant’s solicitors wrote to the defendant council on 15 November 2012 purporting
       to require it to serve a Stop Notice to bring the development to a halt, because the
       pre-commencement conditions had not been properly discharged before the development 
      was started. They also sent a letter before action on 7th December 2012, challenging the 
      continuing failure of the defendant council to take enforcement action. The letter requested
      enforcement action to be considered in the shortest possible time, apparently because of
       the claimed risk of water pollution to a European site. A “firm response” was sought by 
      13 December 2012 and they stated that they were “almost ready to issue a claim for
      judicial review,” having instructed Counsel.

    1. The defendant council’s reply on 13 December 2012 stated that a report from officers 
      on enforcement action would be considered by the Committee on 9 January 2013. 
      On 9 January 2013 the Committee accepted a recommendation that it would not be
      appropriate to take enforcement action at that time.

    1. On 29 January 2013 this application for permission to apply for judicial review was lodged 
      at the court office.

    1. On 13 February 2013 the council’s Planning Committee received a detailed report, 
      which included the observation that,

    “Viridor submitted all the substantive information required by [the defendant council] in order 
    to discharge the conditions prior to commencement.” (para.7.70.)

    The Committee, having taken the environmental information into account, resolved that all the 
    applications under the pre-commencement conditions be approved, and that in the light of those
     decisions it would not be expedient to take enforcement action.

    1. None of the statutory consultees, including the Environment Agency for Wales and the 
      Countryside Commission for Wales, had raised any objection to the grant of approvals
      under the pre-commencement conditions, whether in relation to any effects of the Severn
      Estuary or otherwise.

    1. On 20 March 2013 the Claimant filed an amended statement of facts and grounds. By this she
      sought the following relief:

    1. An order quashing the grant of the subsequent applications approval;
    2. A declaration that the decisions of the Council on 13 February to treat the proposed subsequent
       applications approval as retroactively permitting the unlawful works and rendering enforcement
       action inexpedient was unlawful;
    3. An order requiring the Council to reconsider enforcement action against the unlawful works, or
      An order directing the council to issue an enforcement notice or stop notice, or both, 
      prohibiting further continuation of unlawful development.

    1. In summary, the Claimant’s first three grounds for seeking such relief are that by simultaneously
       (a) granting reserved matters approvals and (b) deciding to take no enforcement action and
       (c) treating those decisions as validating the unlawful works the Interested Party was in effect
       granted retrospective development consent. The process employed by the Defendant, 
      submits the Claimant, denied the public a proper opportunity of comment on the works 
      which were thereby approved. Partly in consequence, it is said, the Council’s committee 
      was deprived of adequate information on the works which it was approving. The process 
      was not the equivalent, in terms of information, clarity or public consultation, of that which 
      would have taken place had an actual application for retrospective permission been made 
      according to the relevant statutory process.

    1. The way in which counsel for the Claimant, Mr Goodman, puts the case is as follows. In granting
        de facto retrospective permission, he submits, the Defendant acted contrary to common law,
       in that inadequate consideration was given to the works which had in fact been undertaken. 
      Moreover, by improperly adopting “a non-statutory ad hoc procedure retrospectively to 
      validate the works,” the proper procedure -- a formal retrospective application under s.
       73A of the Town and Country Planning Act 1990 -- was circumvented, and the public,
       including the Claimant and her associates, were thereby denied the right to be fully 
      consulted and to make representations following such consultation, whereas the 
      opportunity for full public participation would have been ensured if a retrospective 
      application had been made under s. 73A.

    1. Further, the Claimant submits that the Council has made an error in seeking to short-cut 
      the processes required under the Habitats Directive by failing properly to undertake appropriate
       assessment in circumstances where, on the face of its own documents, the test requiring
       appropriate assessment was met. (This refers to a failure to obtain the opinion of the public,
       “as required” by the Regulations, although the words ‘if [the Defendant] considers 
       it appropriate’ are those which are actually the terms of Regulation 61 (4).)

    1. Judge Jarman QC had refused permission for the following reasons. First, he considered that the
       Defendant council was entitled to take the view that, exceptionally, it was appropriate 
      to grant retrospective approval of details under pre-commencement conditions, “… given that 
      substantive details under such conditions were given before works started.” Secondly, detailed 
      planning permission was granted in 2010 “… following a full EIA …” and it had not been 
      shown that the works carried out “… arguably differ from the scheme approved by such
       permission.” Thirdly, the further information which was the subject of further consultation 
      amounted to no more than the non-technical summary and “… a letter from Dwr Cymru.” 
      Lastly, the learned judge observed that the Defendant was entitled to take the view that the
       scheme would have no likely significant effect in respect of “… the Severn Estuary … 
      and so an ‘appropriate assessment’ is not required. The contrary is unarguable.”

    1. Leading counsel for the Defendant, Mr Bird QC, and for the interested party, Mr Holgate QC,
       put their respective cases in different ways, but both submitted in effect that the grounds for 
       this application really boil down to one main point upon which the Claimant relies, namely 
      that although the development received planning permission in 2010, once work had started, 
      approvals to discharge pre-commencement conditions in that permission could not lawfully
       be given by the defendant council in order to comply with the EIA Regulations. For the reasons
       given at length in their skeleton arguments, and trenchantly advanced in oral argument by
       reference to numerous authorities, they submitted that that point, and indeed the whole claim,
       was unarguable.

    1. In addition to the contention that the whole claim is unarguable in law, the Defendant and the
      interested party submitted that (1) the proceedings were pointless as, even if the site were
      returned to its original state, and whole process were reversed and re-started (at incalculably
      massive cost) the outcome would inevitably be identical; (2) the relief sought went far beyond
      any relief the court had power to grant, save perhaps as to the grant of a declaration and 
      possibly of an order for the Defendant Council to re-consider certain matters afresh; and 
      (3) that permission should be refused because of a failure to bring the claim within 3 months 
      of the date when the Claimant says development started. The arguments (a) that only a
      section 73A application could suffice, (b) that a Habitats Regulation Assessment has not been
       properly carried out and (c) that enforcement action should be taken, could all have been
       put forward in July 2012. The delay point was clearly raised in the letter from Viridor’s 
      Solicitors to the Claimant’s Solicitors on 11 February 2013. The Claimant had failed, 
      it was submitted, to put forward any evidence or material to explain, let alone to justify,
      such delay.

    1. On the Claimant’s main point, that the Council could not lawfully approve details under
       the pre-commencement conditions once the development had started, considerable time
       was devoted to discussion of what was referred to as the Whitley principle (Whitley & 
      Sons v. Secretary of State for Wales and Clwyd County Council (1992) 64 P. & C.R. 296).
       The issue in Whitley was whether development authorised by the permission in that case 
      had been ‘begun’, so as to satisfy a condition which imposed a time limit for the 
      commencement of development, and thus to prevent the permission from lapsing under
       section 93(4) of the 1990 Act. It was held that if the building operations relied upon 
      contravened the conditions of the permission, they could not be treated as a commencement
       of the development authorised by the permission. Operations which are not in compliance 
      with the permission constitute a breach of planning control.

    1. The Whitley principle also applies where the conditions of a permission require approval
       of certain details to be obtained before the development may be begun, as in this case. 
      Leading counsel for the Defendant and for Viridor submitted that the Whitley principle should
       not be applied in an unduly rigid manner, where to do so would produce absurd results or 
      run contrary to the purpose of the legislation: see Rastrum Limited v. Secretary of State [2009] EWCA Civ. 1340 para. 15 and Greyfort Properties Ltd v. Secretary of State [2011] EWCA Civ.908, paras. 6-19.

    1. The Defendant Council and the Interested Party submitted that the Claimant had ignored, 
      (or willfully misconstrued as ‘narrow’) certain well-established exceptions to the 
      Whitley principle. It was, they submitted, a recognised principle of planning law and
       practice that, exceptionally, work which is the subject of planning permission may lawfully
       be begun before the approval of details required by pre-commencement conditions, provided
       that the developer has applied for approval before the expiry of the permission, in
       circumstances where (a) the works undertaken comply with the details, and (b) 
      those details are subsequently approved by the local planning authority. In such circumstances
       no fresh application is required even where the time for commencement has expired. 
       Putting it in a slightly different way, if the approvals are applied for before the planning 
      permission expires and are subsequently granted, any irregular development carried out
       before the approvals are obtained is thereby rendered lawful and is to be treated as a
       proper commencement of development. In circumstances such as those in the instant case,
       they submitted, an application for a fresh permission does not need to be made.

    1. The Claimant submits that in asserting that the circumstances fell within the first established
       exception to Whitley, the Defendant

    ... sidestepped the point that applications capable of being lawfully consulted on and
     approved were not made - in the Council’s view - until November 2012, long after
     works commenced.

    Thus, it is submitted, the case did not fall within the defined exception, but requires an extension 
    of the exception. The Interested Party did not in this case
    “… jump the gun to keep a planning permission alive. It simply jumped the gun 
    (presumably for commercial reasons). The underlying rationale of avoiding injustice 
    to a developer who has otherwise done what he could to implement a planning
     permission is therefore absent from this case.

    Counsel for the Claimant relied upon some observations of Lord Woolf in Whitley (at p. 307):

    I should also make it clear that the approach which I have sought to identify is not intended to
     be a charter to developers to ignore conditions which are intended to be complied with 
    before a planning permission is implemented. If it is not already clear, I make it absolutely 
    clear now, that if a developer does not comply with a condition he can have enforcement 
    action or any other available action taken against him. The only consequence of the approach 
    indicated in this judgment is that when the merits of the enforcement proceedings come to be 
    considered, it is necessary to take into account the situation as it exists at the time and in particular whether or not at that time any approval required by condition has been obtained.”

    1. To demonstrate the Claimant’s misconstruction of the Whitley principle, it was submitted that 
      she had misread the Court of Appeal’s decision in Greyfort [2011] EWCA Civ 908. 
      The ‘narrow exceptions’ referred to by counsel for the Claimant were the second and 
      third exceptions to the Whitley principle, neither of which are relevant in the present case. 
      This case is concerned with the first exception to Whitley, dealt with in paragraph 8 of 
      Greyfort, which is not expressed to be, nor to be treated as, a narrow exception. 
      On that premise, the assertion by the Claimant that it was “dubious” as to whether the first 
       exception to Whitley applied, on two grounds unsupported by authority, was wholly lacking 
      in substance. The first point was that works were commenced before a valid application was
      made under the EIA Regulations by the submission of the Non-Technical Summary, which
       was a trivial and insubstantial criticism. The second point was that this is not a case where the
       developer was trying “to preserve a planning permission which would otherwise have expired”
       (in this case in 2015), which amounted to a distinction without a significant difference.

    1. Given that the Council had decided to approve the details submitted and had decided that 
      enforcement action against the works carried out beforehand would be unjustified, no
       rational argument has been advanced as to why the first exception to Whitley should not apply.

    1. Counsel for the Claimant submitted that there had been no misunderstanding of Greyfort, 
      and that the other authorities relied upon by the Defendant and the interested party could 
      be distinguished. In Greyfort, at paragraph 7, reference was made to the case of Leisure 
      Great Britain plc v Isle of Wight Council (1999) 80 P&CR 370. In dealing with the 
      Whitley principle, at 378, Keene J spoke of “a clear legal principle of general application,”
       observing that the court

    “… is not in these cases exercising some general equitable jurisdiction as though it had a 
    broad discretion vested in it where fairness was the only or main criterion”.

    1. It was clear, submitted Mr Goodman, that the circumstances did not fall squarely within an 
      established exception to the Whitley principle. It would be remarkable if a retrospective planning
      consent can be held to have been granted by expansion of an exception to a common law 
      principle rather than by statutory means. On the point that the works are said to be in accordance
      with what was anticipated, and that there is no evidence that they were not, the Claimant’s 
      submission is that it is not enough that works are said to have complied with predicted effects, 
      there had to be an opportunity (a) to challenge that and (b) to make suggestions on different
      approaches, notwithstanding apparent compliance with predicted effects.

    1. A bare denial was no sufficient answer, Mr Goodman submitted, to the Claimant’s complaint 
      that information was not made available as part of a public consultation. The Interested Party had
       not in fact pointed to any such opportunity for consultation, nor had it specified where or when
       the monitoring reports or other data as to the works mentioned in the officers’ report might
       have been the subject of consultation by the public.

    1. As I have already mentioned, leaving aside their attack on the legal merits of the Claimant’s 
      case, the Defendant council and the interested party submit that the Claimant has been
       guilty of inexcusable delay. The essence of the Claimant’s case was that the development
       which was begun on 20 July 2012 was unlawful because no valid approvals under 
      pre-commencement conditions were obtained beforehand, a section 73A application 
      should have been made, and an appropriate assessment should have been carried out. 
      There was no reason why these points could not have been taken by the Claimant in July 2012.
       Indeed, legal action to secure enforcement action was repeatedly threatened from 19 July 
      through to 19 September 2012. It was no answer to this point that the Defendant Council 
      did not formally deal with the enforcement issue at Committee until January and February 
      2013. CATI, including the Claimant, had been complaining about the Council’s failure to 
      take enforcement action from as far back as 19 July 2012. The recommendation to committee
       was that “it would not be appropriate to take enforcement action at this time”. Whether the
      Council resolved “not to take enforcement action at this time” or to “defer consideration of 
       enforcement”, the result was the same: that the Council did not take enforcement action.

    1. I am conscious that the Claimant is in effect the standard bearer for many interested individual
      s who are not personally parties to the litigation, although they may be members of CATI. It 
      may be of assistance, therefore, to explain the restricted nature of the jurisdiction of the 
      Administrative Court. Judicial Review is a public law remedy which enables individuals 
      with proper and sufficient interest to challenge the lawfulness of decisions made by public
      bodies and others exercising public functions.


    1. The principles upon which the court acts include the following. (1) Public bodies such as local 
      planning authorities must have legal authority for their actions. This may be derived from statute 
      or the common law. The public body in question must act within the scope of that legal authority
      (2) Powers must be exercised within the objects and purpose of a statute such as the Town &
       Country Planning Act 1990. (3) Public bodies must take into account all legally relevant 
      considerations and avoid taking into account those that are irrelevant. (4) Fair procedures
       must be followed: whether these are founded on legislation, the common law, or 
      European Union law. Those procedures may, according to context, include requirements 
      to give notice of a proposed decision before making it; to consult and receive written 
      representations; to disclose information before a final decision is reached; to provide oral
       hearings; and to give reasons for a decision. (5) A public body acts unlawfully if it creates a 
      legitimate expectation that a particular procedure will be followed and later seeks to resile 
      from it without an adequate justification. (6) Public bodies must comply with the requirements 
      of European Union law, in accordance with the

    1. The court’s role, when a dispute arises, is to adjudicate on the lawfulness of the decision, 
      procedurally or otherwise. Standards of public administration rest on principles and rules 
      developed by the courts as part of the common law. This is especially so in relation to
       procedural propriety and rationality requirements. Here the court’s role is both to develop
       and apply standards. Against a general background in recent years of increasing expectations
       of fairness, rationality, and justification in public affairs, the courts have developed exacting
       legal standards and have applied these to a wide variety of decision-makers.

    1.  requirement that permission should be refused where there has been delay in applying to the
       court; or where the claimant does not have a sufficient interest in the matter to which the claim
       relates. However, the latter requirement is of limited importance at the permission stage, and 
      does not arise in this case. It is not suggested that the Claimant does not have sufficient standing,
      and that requirement is essentially designed to weed out cranks, mischief-makers 
      and busybodies. The issue of delay is a more substantial hurdle, and it is not unusual for
       permission to be refused on this ground in a clear case. Where, however, the Court is 
      minded to grant permission on the general merits, and there is room for real argument on 
      whether there has actually been delay, or whether an extension of time should be allowed, 
      the issue should be left to be considered at the full hearing.

    1. The most common reason for refusing permission is that the claim is wholly lacking in merit, 
      or unarguable. That test is broadly similar to the practice governing applications for summary 
      judgment, or strike-out applications, in other types of claim, namely that there is “no real
       prospect of succeeding on the claim or issue”.

    1. If permission is granted, it may be subject to conditions or on some grounds only. If a claimant 
      at the substantive hearing seeks to rely on grounds for which permission has been refused, 
      application to do so must be made to the trial judge. At the subsequent full hearing of the claim the judge has a discretion to allow such an application if there is a good reason to do so. Permission may also be refused to pursue a particular remedy, while granting it in relation to other remedies. Permission may be granted in relation to one impugned decision and refused in relation to others.

    1. So far as the principles upon which the court acts in respect of timing and delay, “grounds for making a claim” generally arise when the public authority does an act with legal effect, rather than something which is preliminary to such an act. So in the context of town and country planning, time runs from when planning permission is actually granted rather than from when a local authority adopts a resolution to grant consent. The subjective experience and state of knowledge of the claimant are not relevant in determining a start date, though those facts may be relevant to whether time should be extended. The primary requirement is always one of promptness, and permission may be refused on the ground of delay even if the claim form is filed within three months. The fact that a breach of a public law duty is a continuing one does not necessarily make it irrelevant to take into account the date at which the breach began in considering any question of delay.

    1. There is no general legislative formula to guide the court on issues of delay. Factors taken into
       account include: whether the claimant had prior warning of the decision complained of; and
       whether there has been a period of time between the taking of the decision impugned and its communication to the claimant. Good reasons for delay may include time taken to obtain legal aid; the importance of the point of law at stake; or that the Claimant is awaiting the outcome of consultation. The mere fact that permission is granted does not mean that an extension of time for making the application is given; an express application for extension of time must be made.

    1. Observance of proper procedures is a matter of some importance in planning matters. Some procedural errors may be minor and venial, others may be more fundamental. In the case of a fundamental error, as Lord Denning MR said in the Court of Appeal in Att.-Gen. ex rel. Co-operative Retail Services Ltd. v. Taff Ely Borough Council and Another (1980) 39 P. & C.R. 223; (1979) 250 E.G. 757; [1979] J.P.L. 466, CA, & (1981) 42 P. & C.R. 1 (HL), at the conclusion of his judgment:

    “… there is an important principle of planning law. It is that a grant of planning permission is made in the public interest—so as to ensure that the amenities of our countryside are preserved for the good of all. The protection of the public interest is entrusted to the representative bodies and to the ministers. It would be quite wrong that it should be pre-empted by …” [in that case] “… a mistaken issue by a clerk of a printed form—without any authority in that behalf. When such a mistake is brought to the attention of the court by the Attorney-General, or anyone else with a sufficient interest, the court can and should declare the grant to be void and of no effect. It does not follow that all the consequences that follow from it are void also.”

    The procedural error in that case perhaps represents the top end of the possible scale, whereas the procedural error in the present case would lie -- if indeed there has been error at all -- towards the opposite end. The facts in the instant case are not remotely similar. Nevertheless, some of the circumstances in this case may have generated a legitimate suspicion that when Viridor acted prematurely, there might have been a degree of nervous acquiescence by those officers or members of the Defendant Council dealing with the matter, perhaps having regard to the immense size and importance of the project in financial and other respects. That, in turn, might have resulted in the taking of decisions which are of questionable procedural propriety, even if the same amounted to no more than ‘cutting corners’.

    1. Section 31(6) of the Senior Courts Act 1981 requires the court to consider whether the granting of relief would “be likely to cause substantial hardship to, or substantially prejudice the rights of, any person or would be detrimental to good administration”. In all but the clearest cases, the court will, however, normally postpone consideration of hardship, prejudice and detriment to good administration until the full hearing, though only if the judge granting permission has indicated that this should be so, or if fresh and relevant material relating to delay has arisen in the meantime.

    1. There is obvious force in the submissions made by the Defendant and by the interested party that in practical terms the state of affairs is such that it is inconceivable that any order could be made to restore the site to the status quo before work began. There is likewise force in the point that, when all is said and done, the interested party has a planning permission with several years to run before expiry. It is submitted that even if a retrospective application were made, as the Claimant contends should have been done, the likelihood is that it would be granted, resulting in more or less exactly the current state of affairs. In terms of the relief sought in respect of enforcement action, the court simply cannot substitute its own exercise of discretion for that given by statute to the Defendant Council, and so the court could not grant some of the relief sought.

    1. Those are all points which, independently of the problems over the primary merits of the claim in law, will pose formidable problems for the Claimant in proceeding with a successful claim for judicial review. That said, the actions of the interested party in the first place in proceeding to begin works prematurely, as they did, and of the Defendant Council in protesting only after being prompted to do so by CATI, and then effectively condoning such conduct in the ways in which it subsequently dealt with matters, might conceivably raise matters of legitimate concern, amongst those opposed to the development such as the Claimant, over the procedural propriety of what occurred. Were the court to be satisfied that a significant procedural irregularity had occurred, it is conceivable that limited relief, such as a declaration to that effect, might be granted, not least because it might be thought to be conducive to good administration in the future.

    1. I have considerable reservations as to the Claimant’s likelihood of success on the first three grounds on which the application for permission was renewed, for the reasons given so forcefully and persuasively by leading counsel for the Defendant and for the Interested Party at the hearing. I think, however, that it would be wrong to characterise the case generally as hopelessly unarguable, and the point, in particular, that the process adopted by the Defendant Council amounted to an impermissible extension or addition to any previously-recognised exception to the Whitley principle may indeed be arguable. It must be clearly understood, however, that the matters variously raised by the Defendant and by the Interested Party which are referred to at paragraphs 23 and 44 above are matters which might cause the court to refuse relief even if any merit were to be found in the point.

    1. The fourth ground, in respect of the Habitats Directive, is in my view unarguable. The assessment was on its face, and in substance, merely a screening assessment, and not an “appropriate assessment” and for that reason no obligation, statutory or otherwise, arose to consult the public or to give reasons for not doing so.

    1. I therefore give permission for the first three grounds and refuse permission for the fourth. I also refuse permission to apply for relief in the form of a mandatory order requiring the Defendant council to issue an enforcement notice, for the reason I have already given.

    1. I expressly reserve the issue of delay for the decision of the judge at the substantive hearing. Likewise, I reserve any considerations of hardship, prejudice, and detriment to good administration, until the full hearing.

    1. I direct (under CPR Part 39 PD 6.1) that no tape-recording need be made of this judgment, and that copies of this version may be treated as authentic.

    1. I make the following case management directions.
    General Directions
    1. The defendant and any other person served with the claim form who wishes to contest the claim, or to support it, on additional grounds must file and serve detailed grounds for contesting the claim or supporting it on additional grounds and any written evidence, within 18 days of service of this order.
    2. Any reply and any application by the claimant to lodge further evidence must be lodged within 14 days of the service of detailed grounds for contesting the claim.
    3. The claimant must file and serve a trial bundle not less than 21 days before the date of the hearing of the judicial review.
    4. The claimant must file and serve a skeleton argument not less than 14 days before the date of the hearing of the judicial review.
    5. The defendant and any interested party must file and serve a skeleton argument not less than 7 days before the date of the hearing of the judicial review.
    6. The claimant must file an agreed bundle of authorities, not less than 3 days before the date of the hearing of the judicial review.
    7. For the avoidance of doubt, the issue of delay within the terms of CPR Part 54.5 is expressly reserved for consideration at the substantive hearing in respect of all issues which arise in respect of it.

    Listing Directions
              The case is to be listed for an expedited hearing, with a time estimate of 2 days, before a judge with specialist planning experience, at the Civil Justice Centre, Park Street, Cardiff. If this is not possible on an expedited basis, the Listing Officer in the Administrative Court Office at Cardiff is to make arrangements for the case to be heard at a venue elsewhere.

    The case is not suitable for hearing by a Deputy High Court Judge.